TMEP – Spread 5 B – Lower Mainland Region BC
Project Duration: 09/2022 - 01/2024 (Current)
Scope: Mainline new construction installation of NPS 36.
TC Energy - Depth of Cover Monitoring Program – Central & Southern AB
Project Duration: 06/2022 - 09/2022
Scope: Completed 6200 km of survey monitoring.
TC Energy - Zone 6 Winter Dig Bundle - Southern AB
Project Duration: 03/2022 - 04/2022
Scope: Completed 4 NPS 48 SCC Digs.
TC Energy - Winter Dig Bundle Project - Northern AB
Project Duration: 12/2021 - 03/2022
Scope: Completed 18 NPS 20 SCC / Growth ECOR & Immediate Digs.
TC Energy - Remedial Brushing Project - Northern ON
Project Duration: 10/2021 - 12/2021
Scope: Completed 2400 km of ROW brush clearing within L 100-1, L 100-2 & L 100-3.
TC Energy - CP Remedial Project, - Northern ON
Project Duration: 05/2021 - 11/2021
Scope: Completed 1400 DGB / RGB anode installations along with 110 km of above ground pole lines for L 100-1, L 100-2 & L 100-3.
TC Energy - Brushing Program - Northern AB
Project Duration: 02/2021 - 04/2021
Scope: Completed 1800 km of ROW brush clearing within L 100-1, L 100-2 & L 100-3.
TC Energy - Clearwater CS Suction Valve Replacement Project - Central AB
Project Duration: 02/2021 - 02/2021
Scope: Completed one NPS 30 Suction Valve Replacement.
TC Energy - NGTL NW AB & PRML Winter Dig Project - Northern AB
Project Duration: 12/2020 - 02/2021
Scope: Completed 280 km of winter access ROW building.
TC Energy - CSE Exp Dig Program NONT - Northern ON
Project Duration: 11/2020 - 12/2020
Scope: Completed 2 NPS 30 SCC Digs.
TC Energy – ML Riser Visual Assessment Program – Southern AB / Central SK
Project Duration: 05/2020 - 11/2020
Scope: Completed riser visual inspection on all the B/G & A/G piping within the 12 TC M/S, 10 Sales Tap & 4 C/S stations.
TC Energy – 2019/2020 Winter Bundle 1 AB Dig Program - Central AB
Project Duration: 11/2019 - 05/2020
Scope: Completed 8 NPS 24, 6 NPS 30 & 4 NPS 48 SCC Digs.
TC Energy –2019 Riser Visual Assessment Program - Southern AB /Central SK/Central MB
Project Duration: 05/2019 - 11/2019
Scope: Completed riser visual inspection on all the B/G & A/G piping within the 10 TC M/S, 8 Sales Tap & 6 C/S stations.
TransCanada – 2018 / 2019 STN 102 NONT Underground Leak Severity Program – Northern, ON
Project Duration:11/2018 - 05/2019
Scope: Completed two NPS 42 Suction Valve Replacement along with a NPS 42 slip boar.
TransCanada – 2018 / 2019 STN 86 NONT Underground Leak Severity Program – Northern, ON
Project Duration: 11/2018 - 03/2019
Scope: Completed one NPS 42 Suction Valve Replacement.
TransCanada – 2018 NONT Summer Dig Program – Northern, ON
Project Duration: 05/2018 - 11/2018
Scope: Completed 6 NPS 24 / 8 NPS 30 & 10 NPS 48 SCC Digs.
TransCanada – 2017 Reconnect Program, - Central, AB
Project Duration: 03/2018 - 05/2018
Scope: Completed 6 NPS 8 reconnects & 2 NPS 12 reconnects.
TransCanada – 2018 Bundle 1 W Integrity Dig Program – Northern, AB
Project Duration: 11/2017 - 03/2018
Scope: Completed 8 NPS 48 & 7 NPS 30 SCC / ECOR Integrity Digs.
TransCanada – 2017 PI NPS 48 MLV 13-14-7 LR Program - Central, SK
Project Duration: 11/2017 - 12/2017
Scope: Completed 1 NPS 48 Launcher & Receiver installation.
TransCanada – Ontario SCC / ECOR Integrity Dig Program, - Southern, ON
Project Duration: 10/2017 - 11/2017
Scope: Completed 2 NPS 48 & 1 NPS 30 SCC / ECOR Integrity Digs.
TransCanada - NGTL Tank Integrity Program – Southern AB, SK & MB
Project Duration: 09/2017 - 11/2017
Scope: Completed tank visual inspection within the 14 TC M/S, 6 Sales Tap & 4 C/S stations.
TransCanada - North & Central Alberta 2017 Riser Assessment Program - Northern, AB
Project Duration: 05/2017 - 11/2017
Scope: Completed riser visual inspection on all the B/G & A/G piping within the 15 TC M/S, 7 Sales Tap & 7 C/S stations.
TransCanada - North & Central Alberta 2017 Riser Assessment Program – Central, AB
Project Duration: 01/2017 - 04/2017
Scope: Completed riser visual remediation work on all the B/G & A/G piping within the 11 TC M/S, 4 Sales Tap & 6 C/S stations.
TransCanada - Immediate Integrity Dig Program - Northern, AB
Project Duration: 10/2016 - 12/2016
Scope: Completed armor wrap repair installation on 2 NPS 30 & 2 NPS 48 SCC Digs.
TransCanada - North & Central Alberta 2016 Riser Assessment Program – Central, AB
Project Duration: 05/2016 - 11/2016
Scope: Completed riser visual remediation work on all the B/G & A/G piping within the 8 TC M/S, 8 Sales Tap & 9 C/S stations.
TransCanada - Shaunavon Station Dig - Southern, SK
Project Duration: 04/2016 - 04/2016
Completed / excavated 2 NPS 24 SCC digs.
Enbridge - Integrity Dig Program - Southern, SK
Project Duration: 06/2014 - 03/2016
Scope: Completed / excavated 22 NPS 24, 11 NPS 30, 18 NPS 42 & 24 NPS 48 SCC Digs.
Enbridge - Facility Build Program – Southern, SK
Project Duration: 09/2013 - 05/2014
Scope: Complete all civil (Grades & Slopes) post construction earth work prior to completing the new excavation mainline ditch / HDB road bores (NPS 30) for Line 67 new build facility program.
Husky Energy - Mainline Project - Southern, AB
Project Duration: 04/2013 - 08/2013
Scope: Completed 110 km of mainline open cut excavating for NPS 30.